Quarterly Activities Report for the period ending 31 March 2026

Highlights from the Quarter

With its €2.2 billion ($AU3.9 billion) financing package secured for its flagship Lionheart Project (Lionheart) in Germany's Upper Rhine Valley, Vulcan Energy Resources Ltd. (ASX: VUL) (Vulcan Energy or the Company) has made good progress in its construction activities.

Project Lionheart

Lionheart involves the construction of an integrated lithium and renewable energy project targeting production capacity of 24,000 tonnes of lithium hydroxide monohydrate (LHM), enough for ca. 500,000 electric vehicle batteries per annum, with a co-product of 275 GWh of renewable power and 560 GWh of heat per annum for local consumers, over an estimated 30-year project life[1]. Lionheart represents the first phase of planned production, with future phases also in progress across the Upper Rhine Valley Brine Field.

Health and Safety

Upstream Field Development
Vulcan's new production well (LSC-1), the fifth well in the Lionheart Field Development Plan, was successfully drilled, completed and tested showing strong production flow test performance
Drilling at the sixth well in the Lionheart Field Development Plan (LSC-2) progressed
Well pad construction commenced at the Company's fourth production 'well site'.

Upstream Geothermal and Lithium Extraction Plant
Construction of the interconnected pipeline and power (ICPP) from well infrastructure to geothermal and lithium extraction plant is underway in parallel with tendering, procurement and engineering activities
Execution of bulk earthworks commenced with relocation of overhead power lines progressing
Issuance of the first lithium production permit for Lionheart - the first such licence to be granted in the Upper Rhine Valley Brine Field.

Downstream Lithium Chemicals Plant
Preparation for early civil site works continued including site facilities as well as engineering, tendering and procurement activities.

Corporate

Subsequent Events

Managing Director and CEO, Cris Moreno, commented:

"Vulcan has had a great start to the year as we deliver against the planned execution programme for our flagship Lionheart Project.

"Encouragingly, the lithium market continues going from strength to strength with the need for domestic energy security and critical materials resilience increasingly in focus with government and industry partners.

"Driven by accelerating lithium demand from the electrification of mobility, rapid growth in battery storage for artificial intelligence and data centres and the expanding renewables sector, the tailwinds supporting Vulcan are significant. We intend to move at pace to ensure the Company captures this momentum."

Figure 1: Diagram showing Vulcan business segments that depicts the flow of molecules from upstream to downstream and the various goods and services generated for various applications.

Figure 2: Sunset at the LSC-1 production well site near Landau.

Lionheart Field Development

Drilling of Production/ Re-injection Wells

Figure 3: Construction works at the fourth production site ahead of mobilisation of the V10 rig in H2 2026.


Figure 4: Overview map of Vulcan's Lionheart Project

Geothermal-Lithium Extraction Plant

The Company's combined geothermal and lithium extraction facility has been designed to produce both renewable geothermal energy and lithium chloride (LiCl) from deep geothermal brine. The commercial site, sitting on approximately 10 hectares, is under construction in the Messegelände Südost D12 industrial park in Landau (D12). The second existing Vulcan geothermal plant at Insheim comprises operating wells and produces renewable power that is sold to the grid. The Company's wells produce hot brine, which is transported through a network of pipelines and cables from the well sites to the geothermal and lithium extraction facility and back to the well sites for re-injection.

Landau is also the home to one of Vulcan's existing geothermal plants which comprises operating wells that generate renewable district heating to the community.

Figures 5 and 6: Equipment arriving for site works at the geothermal and lithium extraction facility in Landau.

Lithium chemicals plant

The lithium chemicals processing facility (also known as the central lithium plant) will be the Company's commercial downstream lithium processing hub at Infraserv Park Höchst in Frankfurt, one of Germany's largest major chemical and energy precincts. The lithium chemicals plant will convert LiCl solution from the lithium extraction facility in Landau into battery?quality lithium hydroxide monohydrate (LHM), supporting Europe's push for locally sourced, low?carbon battery materials. The Company has secured relevant permits to build and operate its lithium chemicals plant for Lionheart, with the facility available for separate growth phases as required.

Figure 7: Infraserv Park Höchst, Frankfurt

Figure 8: Central lithium plant site at Infraserv Park Höchst.

Contracts and procurement

Site activities

Technology

Corporate

Financing

Future phases

Ongoing pre-feasibility study work relating to future phase development continued throughout the reporting period in addition to the following:

Mannheim, Germany

The Company aims to deliver baseload geothermal heat to stakeholders in the Mannheim region, while simultaneously extracting lithium. Current activities include:

Ludwigshafen, Germany

Regional work in Upper Rhine Valley Brine Field

Additional ASX Disclosure Information

ASX Listing Rule 5.3.1: Exploration and Evaluation expenditure during the Quarter was €0.4m.

Development expenditure of €76.0 million during the quarter primarily related to the progression of the Lionheart Project. This included payments for the supply and installation of the Organic Rankine Cycle (ORC) power plant, land acquisitions of strategic plots (including D12), and advance and milestone payments to major contractors for engineering, procurement and site?related development activities. Expenditure also included project engineering and procurement activities undertaken to support construction readiness at Lionheart. A detailed breakdown is below:

Development expenditure Quarterly spend €'000
Supply and installation of the Organic Rankine Cycle (ORC) power plant 25.6
Land acquisitions of strategic plots (including D12) 17.1
Vercana drilling campaign (including LSC2) 9.0
Central Lithium Plant (CLP) 7.1
Lithium Extraction Plant (LEP) 4.5
Other Lionheart Project engineering, procurement and site?related development activities 12.7
Total 76.0

ASX Listing Rule 5.3.3: Other than the receipt of the lithium production permit for Lionheart (LiThermEx), no licences were acquired or disposed of during the Quarter. For further information see Table 1 below.

ASX Listing Rule 5.3.5: Payments to related parties of the Company and their associates during the Quarter per section 6.1 of the Appendix 5B amounted to €413,000. This is comprised of an allocation of the Managing Director remuneration of €129,000, Group Chief Financial Officer and Executive Director remuneration of €107,000, Executive Chair remuneration of €106,000 and Non-Executive Director fees of €71,000. Payments to related parties of the Company and their associates during the quarter per section 6.2 of Appendix 5B were nil. Please see the Remuneration Report in the 2025 Annual Report for further details on Directors' Remuneration.

Table 1: Vulcan's integrated lithium and renewable energy project licence table[2]

NAME STATE RESOURCES AREA (KM²) EXPIRY OWNERSHIP AS AT 31 MARCH 2026 CHANGE IN OWNERSHIP TYPE
Rift-Nord RLP Geothermal & lithium 61,83 (VER share), 149.74 km² total 6.2027 50 % VER GmbH, 50 % GET, Vulcan has rights to develop production projects with 100% ownership in the licence area N/A exploration
Landau-Süd RLP Geothermal 19.41 5.2034 100 % VER GmbH N/A production
Ilka RLP Lithium 6.2026 100 % VER GmbH N/A exploration
Insheim RLP Geothermal 19 11.2037 100% Natürlich Insheim GmbH N/A production
LiThermEx[3] RLP Lithium 3.2032 100% Natürlich Insheim GmbH N/A production
Ried Hessen Geothermal, brine & lithium 289.92 7.2027 100 % VER GmbH N/A exploration
Luftbrücke Hessen Geothermal, brine & lithium 207.25 9.2026 100 % VER GmbH N/A exploration
Waldnerturm BW Geothermal, brine & lithium 20.43 12.2026 100 % VER GmbH N/A exploration
Lampertheim II Hessen Geothermal, brine & lithium 1.99 7.2026 100 % VER GmbH N/A exploration
Ortenau II BW Geothermal, brine & lithium 374.1 12.2028 100 % VER GmbH N/A exploration
Mannheim BW Geothermal, brine & lithium 144.49 6.2027 100 % VER Pty Ltd N/A exploration
Taro RLP Geothermal 32.68 9.2027 100% VER GmbH N/A exploration
Lisbeth RLP Lithium 9.2027 100 % VER GmbH N/A exploration
Ludwig RLP Geothermal & lithium 96.34 12.2027 100 % VER GmbH N/A exploration
Therese RLP Geothermal & lithium 81.12 12.2027 100 % VER GmbH N/A exploration
Lampertheim Hessen Geothermal, brine & lithium 108.03 7.2026 100 % VER GmbH N/A exploration
Kerner RLP Geothermal & lithium 72.26 12.2027 100 % VER GmbH N/A exploration
Löwenherz RLP Geothermal & lithium 75.43 12.2026 100 % VER GmbH N/A exploration
Flaggenturm 2023 RLP Geothermal 166.75 12.2027 100 % VER GmbH N/A exploration
Fuchsmantel 2023 RLP Lithium 12.2027 100 % VER GmbH N/A exploration
Darmstadt-West Hessen Brine & lithium 163,09 6.2027 100 % VER GmbH N/A exploration
Kachelhoffa[4] FR Geothermal 463.34 7.2029 100% Vulcan Énergie France N/A exploration
Kachelhoffa minéral FR Lithium 7.2029 100 % Vulcan Énergie France N/A exploration
Cesano IT Geothermal & Lithium 11.46 01.2027 50% Vulcan Energy Italy Pty Ltd., 50 % Enel Green Power N/A exploration


Mineral Resources and Ore Reserves

During the Quarter, there was no change to Vulcan's Mineral Resource or Ore Reserves.


For and on behalf of the Board

Daniel Tydde | Company Secretary


Further information

Jeremy McManus | Head of Investor Relations | jmcmanus@v-er.eu | +61 422 000 675

Judith Buchan | Head of Corporate Communications | jbuchan@v-er.eu | +61 411 597 326

Please contact Vulcan's Legal Counsel Germany, Dr Meinhard Grodde, for matters relating to the Frankfurt Stock Exchange listing on mgrodde@v-er.eu


About Vulcan Energy

Vulcan Energy (ASX: VUL, FSE: VUL) is building the world's first integrated carbon neutral lithium and renewable energy business to decarbonise battery production. Located in the Upper Rhine Valley Brine Field between Germany and France, Vulcan's Lionheart Project (Lionheart) is a lighthouse project for Europe's energy and critical raw material resilience.

Lithium is to be extracted from low impurity geothermal sub-surface brines using Vulcan's industry-leading VULSORB® technology. Naturally heated, the brine powers production and conversion of lithium to battery-quality material by creating a renewable energy co-product for use in operations, with surplus sold into the local energy market. This integration, technology and favourable brine chemistry collectively enables one of the lowest cost lithium operations globally.

Extraction is only the starting point for Vulcan. The Company has reimagined mining using innovation to integrate and capture more of the value chain. The Company has made its positive Final Investment Decision on Lionheart, construction is underway, offtake contracted and further phases of production are in planning.

For more information, please go to www.v-er.eu


Disclaimer

Some of the statements appearing in this announcement may be in the nature of forward-looking statements. You should be aware that such statements are only predictions and are subject to inherent risks and uncertainties. Those risks and uncertainties include factors and risks specific to the industries in which Vulcan operates and proposes to operate as well as general economic conditions, prevailing exchange rates and interest rates and conditions in the financial markets, among other things. Actual events or results may differ materially from the events or results expressed or implied in any forward-looking statement. No forward-looking statement is a guarantee or representation as to future performance or any other future matters, which will be influenced by a number of factors and subject to various uncertainties and contingencies, many of which will be outside Vulcan's control.

Vulcan does not undertake any obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events. No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions or conclusions contained in this announcement. To the maximum extent permitted by law, none of Vulcan, its Directors, employees, advisors or agents, nor any other person, accepts any liability for any loss arising from the use of the information contained in this announcement. You are cautioned not to place undue reliance on any forward-looking statement. The forward-looking statements in this announcement reflect views held only as at the date of this announcement.

This announcement is not an offer, invitation or recommendation to subscribe for, or purchase securities by Vulcan. Nor does this announcement constitute investment or financial product advice (nor tax, accounting or legal advice) and is not intended to be used for the basis of making an investment decision. Investors should obtain their own advice before making any investment decision.


Competent Person Statement

The information in this announcement that relates to estimates of Mineral Resources and Ore Reserves is extracted from the Bridging Engineering Study Results announcement on 16 November 2023 (Bridging Study Announcement) and the Future Phase Pipeline - Mannheim Resources Growth announcement on 9 July 2025[5], both of which are available to view on Vulcan's website at http://v-er.eu. Vulcan confirms, that in respect of the estimates of Mineral Resources and Ore Reserves included in this announcement:

  1. it is not aware of any new information or data that materially affects the information included in the original market announcement, and that all material assumptions and technical parameters underpinning the estimates in the original market announcement continue to apply and have not materially changed; and
  2. the form and context in which the Competent Persons' findings are presented in this announcement have not been materially modified from the original market announcement.

The information in this announcement that relates to Exploration Results is extracted from the "Positive start to Phase One Lionheart Project field development" announcement on 19 November 2025 which is available to view on http://v-er.eu 20 Vulcan's website at http://v-er.eu. Vulcan confirms, that in respect of the Exploration Results included in this announcement: a) it is not aware of any new information or data that materially affects the information included in the original market announcement, and that all material assumptions and technical parameters underpinning the Exploration Results in the original market announcement continue to apply and have not materially changed; and b) the form and context in which the Competent Persons' findings are presented in this announcement have not been materially modified from the original market announcement


Production Targets and Forecast Financial Information

The information in this announcement that relates to production targets is extracted from the Bridging Study Announcement. Vulcan confirms that all material assumptions underpinning the production targets included in the original market announcement continue to apply and have not materially changed.

This announcement contains forecast financial information (including forecast financial information derived from the Company's production targets). This forecast financial information is based on the material assumptions set out in (or referred to in) slide 39 of the Company's ASX announcement titled "Financing and FID presentation" released on 3 December 2025 (Investor Presentation) and the Independent Expert Report included as section 17 to the ASX announcement titled "Information Memorandum" released on 11 December 2024 (Information Memorandum), both of which are available to view on Vulcan's website at http://v-er.eu. Vulcan confirms that those assumptions set out in the ASX announcements referred to above (for the avoidance of doubt, having regard to the extent to which the assumptions referred to in the Information Memorandum have been modified by the updated information set out in (or referred to in) slide 39 of the Investor Presentation) continue to apply and have not materially changed.

The Company believes that it has a reasonable basis for making the forward-looking statements in this announcement (including with respect to forecast financial information).

[1] Based on the Phase One Lionheart production target capacity of 24kt p.a. from Bridging Engineering Study ASX announcement 16th November 2023 and Vulcan internal estimated average EV battery size and chemistry in Europe. Refer to the Competent Person and Production Targets and Forecast Financial Information Statements within this announcement and the Key Risks in Appendix 3 of the Investor Presentation dated 3 December 2025 regarding the risks associated with resource exploration and development projects.

[2] Vulcan's licences as at the date of this report, unless otherwise noted, with the Lionheart licences shaded in grey. Vulcan has a total of 24 licences, with 21 in Germany. The German licences are over 17 separate areas as Insheim and LiThermex, Landau-Süd and Ilka, Lisbeth and Taro, Flaggenturm and Fuchsmantel are separate lithium and geothermal licences over the same respective areas

[3] The receipt of the lithium production permit for Lionheart occurred during the Quarter.

[4] The Company notes the decision of the Nancy Administrative Couty of Appeal against the geothermal permit, and for the lithium exploration permit grant validation and will continue to work in consultation with the government and local authorities.

[5] The Mannheim Announcement relates solely to the lithium brine Resource estimation for the Mannheim sector.