Cabral Gold Provides Update on Construction Progress at Cuiú Cuiú; Project on Track for Q4 2026 Production

13:02 Uhr  |  Newsfile

Vancouver, March 5, 2026 - Cabral Gold Inc. (TSXV: CBR) (OTCQX: CBGZF) ("Cabral" or the "Company") is pleased to provide a construction update regarding its Phase 1 gold-in-oxide heap leach project at the Cuiú Cuiú Gold District, Brazil.

Highlights

Alan Carter, Cabral's President and CEO, commented, "Our Construction team continues to make excellent progress in executing on the 12-month construction program for our Phase 1 gold-in-oxide heap leach project at Cuiú Cuiú. Our team has demonstrated resilience and strong technical capability in successfully dealing with the challenges encountered to date. We have put behind us the uncertainty normally associated with significant earthworks of a construction project, and we are now focused on above-ground construction and plant erection, which is less dependent on weather conditions. The execution of the project plan is proceeding on budget and to schedule, targeting commissioning of the plant in the third quarter of 2026, followed by commercial production at Cuiú Cuiú in the fourth quarter of 2026."

Cuiú Cuiú Construction Update

Detailed Engineering

Project engineering and construction execution drawings continue ahead of plan ensuring these activities are unlikely to impact the critical path.

Major current priorities include;

Procurement and Delivery

Overall procurement of equipment for all major plant equipment is over 90% complete. Notable long-lead items currently being manufactured include the adsorption, desorption, and recovery ("ADR") plant, the mineral sizer, and the various conveyor systems. The ADR plant is in the final assembly stage at Como Engineering in Perth, Australia (Figure 1). After a dry commissioning program in March, the plant will be disassembled and packed in shipping containers for transportation to the site.



Figure 1: The Adsorption, Desorption, and Recovery (ADR) plant at Como Engineering in Perth, Australia,nearing completion, prior to commissioning and shipping to Cuiú Cuiú site

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3900/286357_4824a8e184ebebe6_002full.jpg

Manufacturing of steel structures is progressing with all contracts awarded to local suppliers. The fabrication of the Run of Mine ("ROM") ore bin and related support structures is being prepared for transport to the site, where its delivery is expected by mid March (Figure 2).



Figure 2: Run of Mine (ROM) steel ore bin under fabrication in Itaituba, Brazil

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3900/286357_4824a8e184ebebe6_003full.jpg

Expenditures and schedule are tracking in line with the Pre-Feasibility Study with an effective date of July 29, 2025 (filed under Cabral Gold's profile on Sedar, entitled "Pre-Feasibility Study - NI 43-101 Technical Report, Cabral Gold Inc.").

Infrastructure Improvements and Construction

The area for the permanent mine camp has been cleared and leveled, and construction began in January 2026. The mine camp and project offices will be located within the secured operations area and alongside the new dedicated private airstrip. The new accommodation facilities will have capacity for 136 employees and contractors, and they remain on schedule for completion by the end of March 2026 (Figure 3).



Figure 3: New mine camp currently under construction at Cuiu Cuiu.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3900/286357_4824a8e184ebebe6_004full.jpg

Earthworks on the production plateau are now 95% complete, as are most of the concrete foundations required to support the process equipment due on site in the coming months. The final water and solution storage ponds are currently nearing completion (Figure 4). This critical phase of the project was completed on time and within the allocated budget.



Figure 4: Solution storage ponds on the production plateau at Cuiu Cuiu nearing completion

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3900/286357_4824a8e184ebebe6_005full.jpg

A 9-metre-high Mechanically Stabilized Earth (MSE) retaining wall for the ROM ore reception area was recently completed (Figure 5), making room for the ROM ore bin that will receive ore in preparation for processing.



Figure 5: Run of Mine area of Production Plateau showing recently constructed Mechanically Stabilized Earth (MSE) retaining wall which is 9m high. Cement foundations on left are for mineral sizer and cement bin.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3900/286357_4824a8e184ebebe6_006full.jpg

Project Development Timeline

The Project remains on track and on budget for plant commissioning in Q3, 2026, and commercial production in Q4 2026 (Table 1).



Table 1: GANT chart showing construction schedule for Phase 1 operation at Cuiu Cuiu

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3900/286357_4824a8e184ebebe6_007full.jpg

Safety & Human Resources

The Owners team has worked a total of 37,940 hours so far during 2026 and Contractors have worked a total of 55,685 hours for a total of 93,625 hours with a Lost Time Incident rate ("LTI") of zero.

A total of 283 employees and contractors are currently engaged by the Project (excluding the off-site Ausenco Brazil engineering team and the corporate exploration team), with 100% of the workforce comprised of Brazilians and 70% local residents from the State of Para.

During the coming weeks, the project will see a gradual transition of the workforce from earthmoving to plant erection and construction, which are expected to dominate in the coming months.

Timetable and Next Steps

The project has progressed efficiently through the early construction phase, leveraging the investment in initial works during 2025. Despite more challenging weather conditions in January and February, the project is now 54% complete and on schedule for commissioning in Q3, 2026. Key development milestones in the upcoming months include:

Video Update

The company has included a link on its website to a short video showing of our construction progress. We will update this video each month simultaneously with the release of the monthly update. The link is https://youtu.be/WQ415zAg-2g .

About Cabral Gold Inc.

The Company is a junior resource Company engaged in the identification, exploration, and development of mineral properties, with a primary focus on gold properties located in Brazil. The Company has a 100% interest in the Cuiú Cuiú gold district located in the Tapajós Region, within the state of Pará in northern Brazil. Three main gold deposits have so far been defined at the Cuiú Cuiú project which contain National Instrument ("NI") 43-101 compliant Indicated resources of 12.29Mt @ 1.14 g/t gold (450,200oz) in fresh basement material and 13.56Mt @ 0.50 g/t gold (216,182oz) in oxide material. The project also contains Inferred resources of 13.63Mt @ 1.04 g/t gold (455,100oz) in fresh basement material and 6.4Mt @ 0.34 g/t gold (70,569oz) in oxide material. The resource estimate for the primary material is based on the NI 43-101 technical report dated October 12, 2022. The resource estimate for the oxide material at PDM and MG is based on a NI 43-101 technical report dated October 21, 2024. The resource estimate for the oxide material at Central and Machichie is based on a NI 43-101 technical report ("Updated PFS") dated July 29, 2025.

The Tapajós Gold Province is the site of the largest gold rush in Brazil's history which according to the ANM (Agência Nacional de Mineração or National Mining Agency of Brazil) produced an estimated 30 to 50 million ounces of placer gold between 1978 and 1995. Cuiú Cuiú was the largest area of placer workings in the Tapajós and produced an estimated 2Moz of placer gold historically.

FOR FURTHER INFORMATION PLEASE CONTACT:

"Alan Carter"

President and Chief Executive Officer
Cabral Gold Inc.

Tel: 604.676.5660

Qualified Person and Technical Information

Technical information included in this release was supervised and approved by Brian Arkell, B.S. Geology and M.S. Economic Geology, SME (Registered Member), AusIMM (Fellow) and SEG (Fellow), Cabral Gold's Vice President, Exploration and Technical Services, and a Qualified Person under NI 43-101.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as such term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward-looking Statements

This news release contains certain forward-looking information and forward-looking statements within the meaning of applicable securities legislation (collectively "forward-looking statements"). The use of the words "will", "expected" and similar expressions are intended to identify forward-looking statements. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements. Such forward-looking statements should not be unduly relied upon. The Company believes the expectations reflected in those forward-looking statements are reasonable, but no assurance can be given that these expectations will prove to be correct.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/286357