Rohstoff-Welt.de - Die ganze Welt der Rohstoffe

Atlatsa announces results for the quarter ended March 31, 2015

15.05.2015  |  CNW

Improved cash generating ability; ramp-up of expansion projects on track

First quarter 2015 operational and financial features:

JOHANNESBURG, May 15, 2015 /CNW/ - Atlatsa Resources Corp. ("Atlatsa" or the "Company") (TSX: ATL; NYSE MKT: ATL; JSE: ATL) announces its operating and financial results for the three months ended March 31, 2015. This release should be read together with the Company's unaudited condensed consolidated interim financial statements for the three months ended March 31, 2015 (the "Consolidated Financial Statements") and the related Management Discussion and Analysis of Financial Condition and Results of Operations (the "MD&A") filed on www.sec.gov and www.sedar.com, which are also available at www.atlatsa.com. Currency values are presented in South African Rand (ZAR), Canadian Dollars ($) and United States Dollars (US$).

Harold Motaung, Chief Executive Officer of Atlatsa, said, "The first quarter of 2015 was characterised by Section 54 safety stoppages and a disappointing safety performance at the mine. Production was also impacted by challenges associated with the opencast operation as a result of community unrest in the fourth quarter of 2014. The safety and health of our employees remains one of our key focus areas and we continue to encourage our employees and contractors to work safely at all times."

"The Company was able to generate cash from its operations as well as maintain Bokoni Mine's ramp-up profile at its two key underground development shafts. Capital discipline, cost containment and efficiency improvements remain key focus areas for Atlatsa."

* 4E PGM means platinum group metals comprising: platinum, palladium, rhodium and gold.

Bokoni Mine operating and financial performance

Set out below are summaries of the key operating and financial results for Bokoni Mine and the Company for the quarter ended March 31, 2015.

Operating results

Q1 2015

Q1 2014

% change

Tonnes delivered

t

372,661

395,957

(5.9)

 

Tonnes milled

t

372,896

390,099

(4.4)

 

Recovered grade

g/t milled, PGM

3.6

3.4(1)

4.7

 

PGM oz produced

oz

42,875

42,820

0.1

 

UG2 milled to total milled

%

30.1

32.1

(6.2)

 

Primary development

metres

2,195

2,686

(18.3)

 

Operating cost/tonne milled

ZAR/t

1,381

1,308

(5.6)

 

Operating cost/PGM oz

ZAR/PGM oz

12,013

11,918

(0.8)

Lost Time Injury Frequency Rate (LTIFR)

Per 200,000 hours worked

1.04

0.96(1)

(8.3)

Financial summary

Expressed in Canadian Dollars (000's)

Q1 2015

Q1 2014

% change

Revenue

52,311

53,831

(2.8)

Cash operating costs

55,125

50,859

(8.4)

Cash operating profit

(2,814)

2,972

(194.7)

Cash operating margin

(5.4%)

5.5%

(197.4)

EBITDA(2)

(3,419)

486

(804)

(1) Restated
(2) EBITDA means earnings before net finance costs, income tax, depreciation and amortization. EBITDA is not a recognized measure under International Financial Reporting Standards ("IFRS") and should not be construed as an alternative to net earnings or loss determined in accordance with IFRS as an indicator of the financial performance of Atlatsa or as a measure of Atlatsa's liquidity and cash flows. While EBITDA is a useful supplemental measure of cash flow prior to debt service, changes in working capital, capital expenditures and taxes, Atlatsa's method of calculating EBITDA may differ from other issuers and, accordingly, EBITDA may not be comparable to similar measures presented by other issuers. See the section entitled "Segment Information" of the Consolidated Financial Statements for a reconciliation of EBITDA to net income / (loss).

Safety and health

Bokoni Mine's LTIFR increased to 1.04 per 200,000 hours worked during the quarter. Eight Section 54 safety stoppages were imposed by the South African Department of Mineral Resources (DMR) at the operations, resulting in a loss of 1,325 4E PGM ounces. It remains critical that all employees and contractors operating at Bokoni Mine work safely and adopt the principle of zero harm.

Operational results

Tonnes milled at the mine decreased by 4.4% to 372,896 tonnes, resulting in flat production of 42,875 4E PGM ounces compared to 42,820 4E PGM ounces during the first quarter of 2014. This slight decrease is as a result of safety stoppages at the mine, frequent cuts in electricity supply as well as lower production from the Klipfontein opencast mine. Operations at the eastern section of the Klipfontein opencast mine remain suspended.

Primary development decreased by 18.3% quarter-on-quarter to 2,195 metres as planned, following a strategic decision to reduce development to a level sufficient to meet Bokoni Mine's stoping flexibility requirements. The current primary development rate is expected to be sufficient to meet the requirements of the mine's growth plan.

Recoveries at the concentrator plant decreased by 0.7% to 89.2% and remained constant at 85.8% for the Merensky and UG2 concentrate, respectively. The decrease is as a result of processing of lower grade ore from the opencast operation.

Financial results

Revenue decreased 2.8% quarter-on-quarter to $52.3 million as a result of the 6.5% decrease in the average ZAR PGM basket price for the quarter (ZAR11,569 compared to ZAR12,373).

Total cash operating costs increase of 8.4% is largely attributable to:

Total capital expenditure for Q1 2015 was $3.8 million (compared to $11.2 million for Q1 2014), comprising 23% sustaining capital and 77% project expansion capital associated with the two key ramp-up shaft operations. The decrease in capital expenditure is as a result of a strategic decision by management to reduce costs without compromising Bokoni Mine's development plan.

The Company continued to improve its cash generating ability, with operating activities generating cash of $0.9 million in the first quarter of 2015, compared to $27.1 million utilised by operations in the first quarter of 2014. As at March 31, 2015, Atlatsa had a cash balance of $4.6 million, excluding restricted cash.

Earnings 

The basic and diluted loss deteriorated to 2 cents per share compared to basic and diluted loss of 1 cent per share, in the first quarter of 2014.

Issued share capital

As at March 31, 2015 Atlatsa had 554,288,473 issued and outstanding common shares.

Financial results – Atlatsa

Expressed in Canadian Dollars (000's)

Q1 2015

Q1 2014

% change

Revenue

52,311

53,831

(2.8)

Cost of sales

(63,368)

(60,966)

(3.9)

Gross loss

(11,058)

(7,135)

(55.0)

General and administrative expenses

(2,633)

(3,365)

21.8

Other income

304

399

(23.8)

Operating loss

(13,387)

(10,101)

(32.5)

Net finance costs

(4,862)

(3,900)

(27.1)

Income tax

1,459

1,185

23.2

Loss for the period

(16,790)

(12,816)

(31.0)

Loss attributable to Atlatsa shareholders

(8,869)

(4,877)

(81.9)

Basic loss per share – cents

(2)

(1)

(100.0)

Outlook

Mine management continues to focus on various initiatives to improve operational efficiencies, disciplined capital allocation and cost management, without comprising Bokoni Mine's existing ramp-up plan. Safety remains a focus area for the mine as the safety of all employees and contractors across operations as well as that of our community members, remains of paramount importance to the Company.  

Bokoni Mine back at full production

On May 11, 2015, operations at Bokoni Mine were interrupted by unrest that erupted in the Bokoni Mine area when some members of communities surrounding Bokoni blocked the main road leading to the mine with burning tyres and rocks. The unrest prevented employees from reporting to work which resulted in three days of lost production. Stability was restored to the area on May 14, 2015 and all employees have since returned to work.

Stakeholder engagement is a key pillar of Atlatsa's business ethos. Atlatsa invests in the area through community-based projects and continually encourages community members to utilize existing legitimate structures to engage with the mine.

Change of Sponsor on the JSE Limited

Shareholders are advised that One Capital Sponsor Services Proprietary Limited has been appointed as Sponsor to the Company on the JSE Limited, effective June 1, 2015.

Cautionary note regarding forward-looking information
This document contains "forward-looking statements" within the meaning of the U.S. Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws that are based on Atlatsa's expectations, estimates and projections as of the dates as of which those statements are made, including statements relating to anticipated financial or operational performance. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "may", "will", "outlook", "anticipate", "project", "target", "believe", "estimate", "expect", "intend", "should" and similar expressions.

Atlatsa believes that such forward-looking statements are based on material factors and reasonable assumptions, including the following assumptions: open cast mining and accelerated development of underground shaft systems at Bokoni Mine will have anticipated positive impacts on operations and production; Bokoni Mine will maintain production levels in accordance with mine operating plan; Bokoni Mine operating plan will continue to be implemented as expected and will achieve improvements in production and operational efficiencies as anticipated; the Company will be able to satisfy the terms and conditions of its letter of support from Anglo Platinum, dated November 10, 2014, as described in Section 1.11 "Liquidity" in the MD&A and under "Going Concern" in Note 2 of the Consolidated Financial Statements; the Platreef Projects will continue to be positive; contracted parties provide goods and/or services on the agreed timeframes; equipment necessary for construction and development is available as scheduled and does not incur unforeseen breakdowns; no material labour slowdowns, strikes or community unrest are incurred; plant and equipment functions as specified; geological or financial parameters do not necessitate future mine plan changes; and no geological or technical problems occur.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company's actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These include but are not limited to:

For further information on Atlatsa, investors should review the Company's Annual Report on Form 20-F for the year ended December 31, 2014 and other disclosure documents available at www.sedar.com and with the United States Securities and Exchange Commission, available at www.sec.gov.

SOURCE Atlatsa Resources Corp.



Contact
Queries: On behalf of Atlatsa: Prudence Lebina, Head of Investor Relations, Office: +27 11 779 6800, Email: PrudenceL@atlatsa.com; JSE Sponsor: The Standard Bank of South Africa Limited, Natalie Di-Sante, Office: +27 11 721 6125; Russell and Associates: Pam McLeod, Office: +27 11 880 3924, Email: pam@rair.co.za