Danakali: Notice to Proceed issued to DRA Global

20.12.2019  |  Business Wire

Danakali Ltd. (ASX: DNK, LSE: DNK, Danakali or the Company), is pleased to announce that the Colluli Mining Share Company (CMSC) has issued a Notice to Proceed to DRA Global (DRA), the preferred provider of Engineering, Procurement and Construction Management (EPCM) services for the Colluli Sulphate of Potash Project (Colluli or the Project). The Notice to Proceed is an interim agreement that allows DRA and CMSC to commence the EPCM process. Further, the Colluli Mining Share Company (CMSC) Board has resolved to commence EPCM phases 1 & 2.

DRA is a high quality, multi-disciplinary global project management and engineering group with strong African experience and EPCM delivery capability. The scope of DRA’s contract includes:

EPCM phase 1 & 2 activities will include:

The purpose of the phased EPCM approach is to ensure that CMSC achieves technical, commercial, financial and nameplate requirements that satisfy the economic model, funding criteria and the expectations of all stakeholders. CMSC’s phased EPCM approach follows.

Project Director, Tony Harrington, said: "I am very pleased we will be formalising our partnership with DRA after over a year of quality and positive interactions with their team. With the majority of project funding committed the CMSC Owner’s Team is ready and eager to collaborate with DRA and commence work immediately. This is the moment our personnel and other stakeholders in Eritrea have been waiting for.” (see excerpts from a 2019 interview with Mr. Harrington at http://www.danakali.com.au/investor-relations/asx-announcements)

EPCM phases 1 & 2 - Mobilisation

EPCM phases 3 to 6 - Construction

Production

  • Mobilise EPCM Owner’s Team
  • Finalise geotechnical work
  • Purchase critical equipment, including reverse osmosis plant
  • Investigate optimisation opportunities
  • Develop optimal execution strategy
  • Finalisation of engineering design and development
  • Finalisation of vendor packages
  • Procurement
  • Finalisation and award of site contracts
  • Construction
  • Commissioning and ramp-up
  • Module I – 472ktpa of SOP
  • Modules I & II – 944ktpa of SOP
  • Shipping from the Port of Massawa, Eritrea

2.25 years from commencement of project execution to production

Visit the Company’s website: www.danakali.com

Follow Danakali on LinkedIn: www.linkedin.com/company/danakali-limited

Subscribe to Danakali on YouTube: www.youtube.com/channel/UChGKN4-M4lOvPKxs9b-IJvw

Announcement authorised for release by the board of Danakali.



Contact

Danakali
Niels Wage
Chief Executive Officer
+61 8 6189 8635

William Sandover
Head of Corporate Development & External Affairs
+61 499 776 998

Corporate Broker – Numis Securities
John Prior / James Black / Paul Gillam
+44 (0)20 7260 1000

UK IR/PR – Instinctif Partners
Mark Garraway / Sarah Hourahane / Dinara Shikhametova
danakali@instinctif.com
+44 (0)207 457 2020