Rohstoff-Welt.de - Die ganze Welt der Rohstoffe

Banro Announces Year End 2014 Financial Results

07.04.2015  |  Marketwired

TORONTO, ONTARIO--(Marketwired - Apr 6, 2015) - Banro Corp. ("Banro" or the "Company") (NYSE MKT:BAA)(TSX:BAA) today announced its financial and operating results for the full year 2014 and fourth quarter 2014.

FINANCIAL HIGHLIGHTS

OPERATIONAL HIGHLIGHTS

PROJECT HIGHLIGHTS

All dollar amounts in this press release are expressed in thousands of dollars and, unless otherwise specified, in United States dollars.

''Combined with Q1 2015 production, it is gratifying to receive three consistent quarters of production from Twangiza after the upgrade project at very competitive cash costs with the promise of incremental improvements as the operation optimizes at design capacity," commented Banro CEO and President John Clarke.

The table below provides the summary of financial and operating results for the years ended December 31, 2014 and 2013 as well as the fourth quarter of 2014 and 2013.

(I) FINANCIAL

Q4 2014 Q4 2013 Change
%
2014 2013 Change
%
Selected Financial Data
Revenues 35,178 27,022 30 % 125,436 111,808 12 %
Total mine operating expenses(1) (24,782 ) (23,661 ) 5 % (96,045 ) (92,857 ) 3 %
Gross earnings from operations 10,396 3,361 209 % 29,391 18,951 55 %
Net income 272 2,086 (87 %) 320 1,630 (80 %)
Basic net earnings per share ($/share) 0.00 0.01 (100 %) 0.00 0.01 (100 %)
Key Operating Statistics
Average gold price received ($/oz) 1,202 1,264 (5 %) 1,239 1,389 (11 %)
Gold sales (oz) 29,264 21,379 37 % 101,225 80,497 26 %
Gold production (oz) 29,445 22,858 29 % 98,184 82,591 19 %
All-in sustaining cost per ounce ($/oz)(2) 689 899 (23 %) 781 1,067 (27 %)
Cash cost per ounce ($/oz)(2) 592 813 (27 %) 683 836 (18 %)
Gold margin ($/oz)(2) 610 451 35 % 556 553 1 %
Financial Position
Cash and cash equivalents 1,002 4,452 1,002 4,452
Gold bullion inventory at market value(3) 2,834 6,281 2,834 6,281
Total assets 887,482 822,033 887,482 822,033
Long term debt 200,921 158,599 200,921 158,599
(1) Includes depletion and depreciation.
(2) All-in sustaining cost per ounce, cash cost per ounce and gold margin are non-IFRS measures. Refer to the non-IFRS measures section of this press release for additional information.
(3) This represents 2,350 ounces of gold bullion inventory shown at the December 31, 2014 closing market price of $1,206 per ounce of gold.

(ii) Operational - Twangiza

(iii) Mine under Construction - Namoya

Mine Under Construction - Investment 2014 Change 2013
($000's) (%) ($000's)
Additions(1) 77,055 (54 %) 166,978
Balance as at December 31 414,258 23 % 337,203
(1) 2014 net of pre-commercial revenue of $21,687.

(iv) Exploration

(v) Corporate Development

(vi) Subsequent Events

OUTLOOK

Banro Guidance 2015
Twangiza (oz), full year 100,000 to 110,000
Namoya (oz)(2), full year including pre-commercial production 90,000 to 100,000
Twangiza cash cost per ounce ($US/oz)(1) 650 to 750
Namoya cash cost per ounce ($US/oz)(1), (2) 725 to 825
(1) Cash cost per ounce is a non-GAAP measure. Refer to the non-GAAP measures section of this press release for additional information.
(2) The Namoya ounces include pre-commercial production of 30,000 to 35,000 ounces. Cash cost above only takes into consideration Namoya in commercial production, i.e. H2 2015

In consideration of potentially depressed gold prices in the foreseeable future and the Company's intent to replace and grow depleted ounces, the Company has developed several key objectives for 2015. These objectives are aimed at increasing gold production while containing costs, and increasing the Company's Mineral Resources to potentially prolong the life of its mines thereby increasing shareholder value. These objectives include:

The Company's capital expenditure forecast for 2015 as compared to 2014 is set out below:

Project 2015 Change 2014
($000's) (%) ($000's)
Twangiza Mine(1) 19,000 35 % 14,026
Namoya Mine(1) 4,000 100 % -
Exploration 5,000 (59 %) 12,219
(1) Comprises sustaining capital expenditures for the year.

Twangiza Mine

During the first half of 2014, the Twangiza Mine focused on the completion of the plant expansion project, improving ore delivery and throughput levels in line with the upgraded design capacity of 1.7 Mtpa. Following ore delivery and throughput achievements during the third quarter, whereby 90% of the upgraded design capacity on an annualized rate was achieved, site management's focus shifted to incremental operational efficiencies. Production during the year included two consecutive quarters of record production as well as numerous record setting months with December 2014 production reaching 11,549 ounces. These operational milestones were a result of the successful plant expansion activities including the ROM Pad sheltered storage which effectively mitigated the adverse impact that the rainfall associated with the wet season has previously had on operating performance.

TWANGIZA MINE 2014 H2 2014 H1 2014 2013 Prior Year
Change %
Gold sales (oz) 101,225 56,261 44,964 80,497 26 %
Gold produced (oz) 98,184 56,616 41,568 82,591 19 %
Material mined (t) 3,595,645 1,996,373 1,599,272 4,116,657 (13 %)
Ore mined (t)(1) 1,927,744 1,146,144 781,600 1,758,972 10 %
Valley fill mined (t) 49,854 - 49,854 - 100 %
Waste mined (t) 1,618,047 850,229 767,818 2,357,685 (31 %)
Strip ratio (t:t)(2) 0.84 0.74 0.98 1.35 (38 %)
Ore milled (t)(1) 1,358,726 765,381 593,345 1,023,981 33 %
Head grade (g/t)(3) 2.70 2.80 2.56 2.98 (9 %)
Recovery (%) 83.00 81.81 84.59 83.80 (1 %)
Cash cost per ounce ($US/oz)(4) 683 605 781 836 (18 %)
(1) The difference between ore mined and ore milled is, generally, the result of the stockpiling of lower grade ore.
(2) Strip ratio is calculated as waste mined divided by ore mined.
(3) Head grade refers to the indicated grade of ore milled.
(4) Cash cost per ounce is a non-IFRS measure. Refer to the non-IFRS measures section of this press release for additional information.

In H2 2014, with the completion of the plant expansion activities, Twangiza increased productivity levels towards steady state operations. The steady state operating productivity has allowed Twangiza to reduce cash costs by 23% from $781/oz in H1 2014 to $605/oz in H2 2014. The improved operating results are driven by the ability for the operations to increase mining and milling productivity, a 25% and 29% increase in tonnage, respectively, while maintaining similar gross expenditures. Going forward, Twangiza will continue to focus on achieving incremental efficiencies through process optimization to further enhance the steady state operations.

Gross spending and unit costs for 2014 full year and fourth quarter in comparison to 2013 are as follows:

Mine Operating Costs (In '000s) Cost per tonne Milled ($/t)
2014 Q4 2014 2013 Q4 2013 2014 Q4 2014 2013 Q4 2013
Mining Costs 15,742 4,600 15,039 5,079 11.6 12.4 14.7 18.0
Processing Costs 35,119 9,415 32,479 8,432 25.8 25.4 31.7 29.8
Overhead 19,390 6,298 21,542 6,041 14.3 17.0 21.0 21.4
Inventory Adjustments (1,103 ) (2,997 ) (1,755 ) (2,173 ) (0.8 ) (8.1 ) (1.7 ) (7.7 )
Total Mine operating cost 69,148 17,316 67,305 17,379 50.9 46.7 65.7 61.5
Total tonnes milled (tonnes) 1,358,726 370,881 1,023,981 282,831

Gross spending and unit costs for 2014 full year in comparison to 2013 full year are as follows:

Mine Operating Costs (In '000s) Cost per tonne Milled ($/t)
2014 2013 Change % 2014 2013 Change %
Mining Costs 15,742 15,039 5 % 11.6 14.7 (21 %)
Processing Costs 35,119 32,479 8 % 25.8 31.7 (19 %)
Overhead 19,390 21,542 (10 %) 14.3 21.0 (32 %)
Inventory Adjustments (1,103 ) (1,755 ) (37 %) (0.8 ) (1.7 ) (53 %)
Total Mine operating cost 69,148 67,305 3 % 50.9 65.7 (23 %)
Total tonnes milled (tonnes) 1,358,726 1,023,981 33 %

Mining

A total of 1,027,311 tonnes of material (Q3 2013 - 1,168,875 tonnes) were mined during the three month period ended September 30, 2014. Total ore mined was 589,288 tonnes (Q3 2013 - 494,535 tonnes). The strip ratio for the third quarter of 2014 fell to 0.74 as compared to 1.36 during the corresponding period in 2013 in accordance with the mine schedule which drove the mining cost per tonne milled from $14.9 to $8.7 per tonne.

Processing & Engineering

For the year ended December 31, 2014, the plant at the Twangiza Mine processed 1,358,726 tonnes of ore (2013 - 1,023,981 tonnes), representing a 33% increase over the prior year. Increased throughput levels reduced the processing cost per tonne milled from $31.7 per tonne to $25.9 per tonne or a decrease of 18%. Throughput in the second half of 2014, following the completion of the plant expansion, increased to over 90% of the upgraded design capacity. Improved mill productivity was assisted by dryer weather conditions than the previous year, and dryer material available aided by the new sheltered ROM storage area along with improvements in pre-screening and ore crushing circuits. Recoveries during the year decreased marginally compared to the prior year to an average rate of 83.0% (2013 - 83.8%) driven mainly by the processing of lower head grade ore. With the achievement of design throughput levels following the expansion, site management focus transferred to incremental operational efficiencies to increase throughput on a consistent basis and improve recoveries. The processing costs were $2.7 million higher compared to 2013 as a result of the 33% increase in throughput, partially offset by lower consumption of mill consumables per tonne processed.

Twangiza Plant Optimization and Expansion

The Twangiza plant upgrade was completed at the end of April 2014, expanding the plant throughput capacity to 1.7 Mtpa. The upgrade was commissioned during the second quarter of 2014, enabling the plant throughput to ramp up to over 90% of design throughput. Site management continues to optimize the plant in order to incrementally increase the benefits from upgrade program.

Sustaining Capital Activities

Throughout 2014, project capital at Twangiza totaling $9,945 included plant expansion activities, ROM Pad roofing, mobile mine equipment and the Tailings Management Facility ("TMF"). Capital spending decreased throughout the year as the plant expansion activities were completed including the ROM Pad roofing.

During 2014 and subsequently up to the date of this press release, the following progress was made in the key areas indicated below with respect to sustaining capital activities at the Twangiza Mine:

Cash Cost and All-in sustaining costs

Cash costs per ounce for the fourth quarter of 2014 were significantly lower than the prior year period, primarily due to increased sales of 7,893 ounces or 37%, due to increased production over the fourth quarter of 2013, while gross spending decreased slightly as a result of achieved operational efficiencies. The all-in sustaining costs decreased from $1,202 in Q4 2013 to $689 per ounce in Q4 2014, mainly due to the lower cash costs as well as contributions from reduced capital expenditures in the fourth quarter of 2014.

Cash Cost per ounce sold ($US/ounce) ($US/ounce)
2014 2013 Change % 2014 2013 Change %
Mining Costs 156 187 (17 %) 157 238 (34 %)
Processing Costs 347 403 (14 %) 322 394 (18 %)
Overhead 190 268 (29 %) 209 283 (26 %)
Inventory Adjustments (9 ) (22 ) (59 %) (96 ) (102 ) (6 %)
Total cash costs per ounce 683 836 (18 %) 592 813 (27 %)
Total ounces sold (ounces) 101,233 80,497 26 % 29,272 21,379 37 %
All-in sustaining costs per ounce 781 1,067 (27 %) 689 1,202 (43 %)

Namoya - Mine under Construction

During the first half of 2014, Namoya development activity progressed towards the completion of construction of the hybrid plant and the subsequent commissioning. During the hot commissioning activities, the Company identified that the Namoya hybrid CIL/heap leach plant was unable to run at design capacity as the percentage of fine material was found to be higher than expected, and as such, higher than the hybrid plant was designed to process. During the third quarter of 2014, management worked with internal expertise and external consultants in order to evaluate, assess and determine a remediation plan to address the issues identified during the hot commissioning stage and best utilize the Namoya Mine. The Company determined that the most appropriate course of action was the addition of a traditional agglomeration drum to the existing circuit while continuing to evaluate the most optimal manner to utilize the CIL circuit. During the fourth quarter of 2014, a lightly used agglomeration drum was procured and transported into the region with delivery to site occurring in early January 2015. This procurement significantly reduced the time requirements of procuring and shipping a new drum for Namoya which is estimated to have taken in excess of 12 months. Processing continued at Namoya during the procurement process through the stacking of semi-agglomerated material through the addition of cement on the transport conveyors to the stacker.

The agglomeration drum was installed and successfully commissioned at the beginning of February 2015. Stacking levels are expected to increase to up to 190,000 tonnes per month following the ramp up towards commercial production levels.

Mining continued at the Seketi and Mwendamboko pits throughout 2014 comprising 2,745,530 tonnes of material of which 1,103,611 tonnes were ore at a strip ratio of 1.49. Management slowed down mining activities during the third quarter due to a lower achievable feed rate through the wet scrubbing circuit. During the fourth quarter, mining activities returned to levels more consistent with the first two quarters, mining 343,753 tonnes of ore at a strip ratio of 1.08 for total material of 715,012 tonnes. In addition to the continuation of mining activities at more normal levels during the fourth quarter of 2014, the mining fleet began activities for the opening of the Kakula pit for grade control and mining activities in 2015.

Additions to Mine under Construction during 2014 consisted of the completion construction, costs associated with initial commissioning activities, work performed in the determination of the optimal remediation plan as well as pre-commercial operating losses due to the mine operating at levels which are below break-even. There were no significant capital amounts spent on project construction or on the acquisition of new property, plant and equipment in the second half of the year, with the exception of costs associated with the agglomeration drum.

During 2014, the Namoya mine produced 18,282 ounces of gold from a total of 565,350 tonnes of ore, stacked and sprayed on the heap leach pads and processed through the CIL circuit, at an indicated head grade of 2.13 g/t Au. During the fourth quarter of 2014, Namoya produced 8,791 ounces through the stacking of 218,248 tonnes of semi-agglomerated material on the heap leach pads. The CIL circuit was not utilized during the fourth quarter as management's main focus remained on the heap leach operation. Namoya's production will continue to benefit incrementally from the increasing stacking rates that are being achieved as the heap leach curve progresses toward steady state operating levels.

Exploration

Consistent with the Company's focus on cash flow management during the completion of development at Namoya and the expansion activities at Twangiza, exploration work during the year 2014 was comprised of low level exploration and ground maintenance activities in the Twangiza Regional (Mufwa), Kamituga, Lugushwa and Namoya projects. Low level exploration activities included geological mapping, channel and trench sampling, rock chip sampling and limited orientation induced polarization survey works.

To support the Twangiza and Namoya operations, near term exploration will focus on the following:

Qualified Person

Daniel K. Bansah, the Company's Head of Projects and Operations and a "qualified person" as such term is defined in National Instrument 43-101, has approved the technical information in this press release.

NON-IFRS MEASURES

Management uses cash cost, all-in sustaining cost, gold margin and EBITDA to monitor financial performance and provide additional information to investors and analysts. These metrics do not have a standard definition under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. As these metrics do not have a standardized meaning, it may not be comparable to similar measures provided by other companies. However, the methodology used by the Company to determine cash cost per ounce is based on a standard developed by the Gold Institute, which was an association which included gold mining organizations, amongst others, from around the world.

The Company defines cash cost, as recommended by the Gold Institute standard, as all direct costs that the Company incurs relating to mine production, transport and refinery costs, general and administrative costs, movement in production inventories and ore stockpiles, less depreciation and depletion. Cash cost per ounce is determined on a sales basis.

Cash Cost 2014 Q4 2014 2013 Q4 2013
($000's) ($000's) ($000's) ($000's)
Mine operating expenses 96,045 24,782 92,857 23,661
Less: Depletion and depreciation (26,897 ) (7,466 ) (25,552 ) (6,282 )
Total cash costs 69,148 17,316 67,305 17,379
Gold sales (oz) 101,225 29,264 80,497 21,379
Cash cost per ounce ($/oz) 683 592 836 813

The Company defines all-in sustaining costs as all direct costs that the Company incurs relating to mine production, transport and refinery costs, general and administrative costs, movement in production inventories and ore stockpiles, less depreciation and depletion plus all sustaining capital costs (excluding exploration). All-in sustaining cost per ounce is determined on a sales basis.

All-In Sustaining Cost 2014 Q4 2014 2013 Q4 2013
($000's) ($000's) ($000's) ($000's)
Mine operating expenses 96,045 24,782 92,857 23,661
Less: Depletion and depreciation (26,897 ) (7,466 ) (25,552 ) (6,282 )
Total cash costs 69,148 17,316 67,305 17,379
Sustaining capital 9,945 2,844 18,586 1,838
All-in sustaining cash costs 79,093 20,160 85,891 19,217
Gold sales (oz) 101,225 29,264 80,497 21,379
All-in sustaining cash cost per ounce ($/oz) 781 689 1,067 899

The Company defines gold margin as the difference between the cash cost per ounce disclosed and the average price per ounce of gold sold during the reporting period.

Banro calculates EBITDA as net income or loss for the period excluding: interest, income tax expense, and depreciation and amortization. EBITDA is intended to provide additional information to investors and analysts. It does not have any standardized meaning prescribed by IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. EBITDA excludes the impact of cash costs of financing activities and taxes, and the effects of changes in operating working capital balances, and therefore is not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate EBITDA differently. A reconciliation between net profit for the period and EBITDA is presented below:

EBITDA 2014 2013 2012
($000's) ($000's) ($000's)
Net income/(loss) 320 1,630 (4,561)
Interest 17,488 7,061 1,070
Taxes - - -
Depletion and depreciation 26,985 25,603 8,096
EBITDA 44,793 34,294 4,605

Year End 2014 Financial Results Conference Call Information

Banro will host a conference call at 11:00AM EST on April 7, 2015. Please use the following dial in numbers:

Year End 2014 Financial Results Conference Call Information

Toll Free (North America): +1-877-291-4570
Toronto Local & International: +1 647-788-4919

Year End 2014 Financial Results Conference Call REPLAY

Toll Free Replay Call (North America): +1 800-585-8367 Conf ID: 18833539
Toronto Local & International: +1 416-621-4642 Conf ID: 18833539

The conference call replay will be available from 2:00PM EST on April 7, 2015 until 11:59PM EST on April 21, 2015.

For further information regarding this conference call, please contact Banro Investor Relations or visit the Company website, www.banro.com.

Banro Corp. is a Canadian gold mining company focused on production from the Twangiza mine, which began commercial production September 1, 2012, and completion of its second gold mine at Namoya located approximately 200 kilometres southwest of the Twangiza gold mine. The Company's longer term objectives include the development of two additional major, wholly-owned gold projects, Lugushwa and Kamituga. The four projects, each of which has a mining license, are located along the 210 kilometre long Twangiza-Namoya gold belt in the South Kivu and Maniema provinces of the Democratic Republic of the Congo (the "DRC"). Led by a proven management team with extensive gold and African experience, the initial focus of the Company is on the mining of oxide material, which has a low capital intensity to develop but also attracts a lower technical and financial risk to the Company. All business activities are followed in a socially and environmentally responsible manner.

Cautionary Note to U.S. Investors

The United States Securities and Exchange Commission (the "SEC") permits U.S. mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. Certain terms are used by the Company, such as "Measured", "Indicated", and "Inferred" "Resources", that the SEC guidelines strictly prohibit U.S. registered companies from including in their filings with the SEC. U.S. Investors are urged to consider closely the disclosure in the Company's Form 20-F Registration Statement, File No. 001-32399, which may be secured from the Company, or from the SEC's website at www.sec.gov/edgar.shtml.

Cautionary Note Concerning Mineral Resource and Mineral Reserve Estimates

The Company's Mineral Resource and Mineral Reserve figures are estimates and no assurances can be given that the indicated levels of gold will be produced. Such estimates are expressions of judgment based on knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time may significantly change when new information becomes available. While the Company believes that Mineral Resource and Mineral Reserve estimates are well established, by their nature Mineral Resource and Mineral Reserve estimates are imprecise and depend, to a certain extent, upon statistical inferences which may ultimately prove unreliable.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no certainty that Mineral Resources can be upgraded to Mineral Reserves through continued exploration.

Due to the uncertainty that may be attached to Inferred Mineral Resources, it cannot be assumed that all or any part of an Inferred Mineral Resource will be upgraded to an Indicated or Measured Mineral Resource as a result of continued exploration. Confidence in the estimate is insufficient to allow meaningful application of the technical and economic parameters to enable an evaluation of economic viability worthy of public disclosure (except in certain limited circumstances). Inferred Mineral Resources are excluded from estimates forming the basis of a feasibility study.

Cautionary Note Concerning Forward-Looking Statements

This press release contains forward-looking statements. All statements, other than statements of historical fact, that address activities, events or developments that the Company believes, expects or anticipates will or may occur in the future (including, without limitation, statements regarding estimates and/or assumptions in respect of the closing of the Twangiza gold forward sale and Namoya stream transactions, future gold production (including the timing thereof), costs, cash flow and gold recoveries, Mineral Resource and Mineral Reserve estimates, potential Mineral Resources and Mineral Reserves and the Company's development and exploration plans and objectives) are forward-looking statements. These forward-looking statements reflect the current expectations or beliefs of the Company based on information currently available to the Company. Forward-looking statements are subject to a number of risks and uncertainties that may cause the actual results of the Company to differ materially from those discussed in the forward-looking statements, and even if such actual results are realized or substantially realized, there can be no assurance that they will have the expected consequences to, or effects on the Company.
Factors that could cause actual results or events to differ materially from current expectations include, among other things: failure to complete the Twangiza gold forward sale and Namoya stream transactions; uncertainty of estimates of capital and operating costs, production estimates and estimated economic return of the Company's projects; the possibility that actual circumstances will differ from the estimates and assumptions used in the economic studies of the Company's projects; failure to establish estimated mineral resources and mineral reserves (the Company's mineral resource and mineral reserve figures are estimates and no assurance can be given that the intended levels of gold will be produced); fluctuations in gold prices and currency exchange rates; inflation; gold recoveries being less than those indicated by the metallurgical testwork carried out to date (there can be no assurance that gold recoveries in small scale laboratory tests will be duplicated in large tests under on-site conditions or during production); uncertainties relating to the availability and costs of financing needed in the future; changes in equity markets; political developments in the DRC; lack of infrastructure; failure to procure or maintain, or delays in procuring or maintaining, permits and approvals; lack of availability at a reasonable cost or at all, of plants, equipment or labour; inability to attract and retain key management and personnel; changes to regulations affecting the Company's activities; the uncertainties involved in interpreting drilling results and other geological data; and the other risks disclosed under the heading "Risk Factors" and elsewhere in the Company's annual report on Form 20-F dated April 6, 2015 filed on SEDAR at www.sedar.com and EDGAR at www.sec.gov. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Although the Company believes that the assumptions inherent in the forward-looking statements are reasonable, forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein.

For further information, please visit our website at www.banro.com.



Contact

Banro Corp.
Joel Friedman
Manager, Finance
+1 (416) 366-3396 or +1-800-714-7938, Ext. 3396
info@banro.com
www.banro.com