Highlights Phase 1 construction at Hombre Muerto West completed, a key inflection point as Galan transitions from developer to producer Plant electrical and mechanical systems testing complete, wet commissioning phase to commence soon A$40 million institutional placement completed at A$0.41 per share to fund the Phase 1 capacity expansion from 4 ktpa LCE to 5.2 ktpa LCE, working capital and to fund exploration activities [...]
Highlights: Phase 1 construction at Hombre Muerto West now complete Production to start at 4 ktpa LCE, works to expand production capacity to 5.2 ktpa LCE soon to commence All major processing infrastructure installed, including nanofiltration plant Project transitioning into testing and commissioning phase Significant brine inventory of circa 10,000 t LCE ready for processing by end of April 2026 First lithium chloride [...]
Highlights: Phase 1 construction now approximately 92% complete Nanofiltration plant assembly progressing to plan Construction expected to complete in the short term, transitioning to testing and commissioning Nanofiltration plant commissioning with raw brine expected to follow successful testing Significant brine inventory ready for processing First lithium chloride concentrate in H1 2026, first shipment H2 2026 Galan [...]
Highlights: Nanofiltration plant successfully delivered to HMW site Galan and Authium teams have commenced on-site assembly. Assembly expected to be completed over the coming weeks Evaporation ponds for Phase 1 operations completed Overall Phase 1 construction now approximately 85% complete First processed brine expected early Q2 2026. First lithium chloride concentrate targeted in H1 2026 Galan Lithium Ltd. is pleased to [...]
Highlights: Galan has received firm commitments to raise A$40 million via an institutional placement at A$0.41 per share, a 2% premium to the 5-day VWAP Directors of the Company have separately committed to subscribe for an additional A$1 million subject to shareholder approval Placement was strongly supported by existing substantial shareholder Clean Elements as well as global institutional and sophisticated investors [...]
Galan Lithium Ltd. confirms the formal appointment of Mr Ofer Amir, Founder of the Clean Elements Fund, to its Board as a Non-Executive Director as foreshadowed in the ASX announcement dated 5 November 2025. Mr Amir brings strong European capital markets expertise to Galan and the Board welcomes his appointment. Further, Katherine Garvey has been appointed as Galan's new Company Secretary, replacing Mr Mike Robbins who [...]
Highlights Phase 1 construction at Hombre Muerto West on track for first production in H1 2026, well timed to take advantage of a lithium market recovery Strategic expansion of Greenbushes South tenure Early completion of the second tranche of the Clean Elements leading to a strong financial position with cash of $15 M. , no debt and an undrawn US$ 6 M. prepayment facility Galan Lithium Ltd. presents its Quarterly [...]
Highlights: Nano-filtration plant has been assembled and tested off-site and is now in transit to Hombre Muerto West Phase 1 construction activities at HMW continue to advance toward completion, ahead of expected first production of lithium chloride in H1 2026 Galan Lithium Ltd. is pleased to provide an update on the progress of its Phase 1 construction activities for HMW, as it advances towards its final stages [...]
Galan Lithium Ltd. is pleased to advise that it has now received the second and final A$10 million tranche of the previously announced investment from the Clean Elements Fund . The accelerated settlement of the second tranche marks the successful completion of the Clean Elements A$20 million placement. The proceeds provide the final equity component required to fund construction of Phase 1 of the Company's Hombre Muerto [...]
Highlights Successful completion of due diligence by the Clean Elements Fund confirming HMW's world-class status; $20 million placement to proceed with full and final settlement due by November. RIGI incentive regime approved by the Argentine Government for the HMW Project, providing fiscal stability and significant long-term benefits. Advancement of Phase 1 construction at Hombre Muerto West , including completion of [...]
Highlights: Grant of E70/4889 secures tenure directly over the mineralising fault zone controlling the world-class lithium deposit at Greenbushes. High-impact program planned to test structural targets and assess mineralisation continuity into Galan's Greenbushes South holdings . Galan Lithium Ltd. is pleased to announce that it has been granted exploration licence E70/4889, together with prospecting licences P70/1702 [...]
Highlights: Site construction activities in Argentina progress with Pond 4 design complete Authium advances nano-filtration plant construction in workshop in Sydney; general equipment assembly to commence Testwork confirms excellent impurity separation and successful stress testing of filtration elements Galan Lithium Ltd. is pleased to provide an update on the progress of Phase 1 construction at its Hombre Muerto West [...]