E3 Lithium has entered into an Asset Purchase and Sale Agreement with an arm's length private company, to sell the Company's non-core, Saskatchewan based, Estevan Lithium District assets for a total cash consideration of US$4.296 million. While E3 sees the long-term development potential of the Estevan lithium district, the Company is prioritizing the commercial development of its Clearwater Project, located in Alberta's [...]
E3 Lithium has produced battery grade lithium carbonate while commissioning Phase 1 of its Demonstration Facility. Additionally, E3 has updated its corporate presentation which is now available on its website. The successful production of battery grade lithium carbonate from the Phase 1 commissioning confirms E3's Demonstration Equipment is fully functional and the field site for Phase 1 is fully operational along the [...]
E3 Lithium has received approval of its required permits from the Alberta Energy Regulator to advance Phase 2 of its Clearwater Project Demonstration Facility. Phased Approach to the Clearwater Demonstration Facility The Demonstration Facility is being completed in three phases, with Phase 1 currently being commissioned as announced on Sept 2, 2025. Phase 2 of the Demonstration Facility involves drilling a production and [...]
E3 Lithium announces that commissioning of Phase 1 of the Demonstration Facility is underway and on schedule. Phase 1 involves operating the 30-column DLE system and polishing and purification equipment. As previously stated, the objective of Phase 1 is to fully operationalize the DLE System and Purification Units to produce a high-quality lithium chloride, which will support the production of battery-grade lithium [...]
E3 Lithium filed its Consolidated Financial Statements for the three-month period ended June 30, 2025, and the accompanying Management's Discussion and Analysis on SEDAR. E3 Lithium has updated its corporate presentation, and along with the financial statements, MD&A, it will be available on E3 Lithium's website. Demonstration Facility Makes Significant Progress During the Quarter, Q3 Commissioning on Target On April 16 [...]
E3 Lithium is progressing towards final inspection and commissioning of Phase 1 of the Demonstration Facility. This press release features multimedia. Demonstration Equipment Being Assembled on Site The goal of Phase 1 is to fully operationalize the DLE system and associated polishing and purification units to produce a high-quality lithium chloride, which will support the production of battery-grade lithium carbonate [...]
E3 Lithium is pleased to announce that it has filed a National Instrument 43-101 - Standards of Disclosure for Mineral Projects independent technical report for its Garrington District project. The Garrington Report titled "NI 43-101 Technical Report for the Garrington District Lithium Resource Estimate" is dated July 18, 2025, has an effective date of June 25, 2025, and the mineral resource estimate was previously [...]
E3 Lithium is pleased to announce the on-schedule arrival of equipment for the Demonstration Facility at the Clearwater Project site, including the 30-column Direct Lithium Extraction system and associated polishing and purification units. This equipment will be used for both Phase 1 and Phase 2 of the planned testing at the Demonstration Facility. This press release features multimedia. View the full release here [...]
E3 Lithium is pleased to announce that all items of business were approved at its Annual General and Special Meeting of shareholders held on July 2, 2025, and that the Board of Directors has subsequently elected a Chairperson and appointed a new Chief Financial Officer. Results of the Meeting At the Meeting, Shareholders voted in favour of the following, as described in the Company's Management Information Circular dated [...]
E3 Lithium is pleased to release an updated mineral resource report for its Garrington District in central Alberta. The NI 43-101 Technical Report for the Garrington District Lithium Resource Estimate outlines an updated Measured and Indicated mineral resource estimate of 5.0 million tonnes of lithium carbonate equivalent Outline of E3 Lithium's Garrington District and Bashaw District Permit Areas Highlights: The [...]
E3 Lithium has set the Annual General Meeting date to July 2, 2025. AGM Details: The Annual General Meeting of Shareholders will be held on Wednesday, July 2, 2025, at 10am. The Notice of the Meeting information will be distributed shortly to all shareholders, will also available under the Company's profile on SEDAR and available on the Company website. We look forward to any interested shareholders attending the AGM [...]
E3 Lithium is pleased to provide a progress update on its Demonstration Facility. The Demo Facility is planned to be brought on stream in three phases through the second half of 2025 and into 2026. The lithium extraction equipment comprising of the 30-column Direct Lithium Extraction system, as well as the purification and concentration equipment is now fully fabricated and undergoing final checks. The heart of the [...]