Aya Gold & Silver Inc. is pleased to report that it has entered into non-binding term sheets for the spinout of its Amizmiz Gold Project in the Kingdom of Morocco and the granting of an option on its Tijirit Project in the Islamic Republic of Mauritania to Mx2 Mining , a new North Africa-dedicated gold growth company backed by Aya with the participation of Richard Clark as its Executive Chairman and Adam Spencer as its [...]
Aya Gold & Silver Inc. today provided an update on construction progress at its Zgounder Silver Mine in the Kingdom of Morocco. The expansion project was 98% complete as at August 30, fully funded, and on budget. The Corporation's engineering, procurement, and construction partner, Duro Felguera , encountered issues during commissioning of the hydraulic unit of the ball mill. As a result of these issues, DF recently [...]
Aya Gold & Silver Inc. is pleased to report additional high-grade silver drill results from its at-depth drill exploration program at the Zgounder Silver Mine in the Kingdom of Morocco. Highlights In the Central Zone from the 1,950m level: hole DZG-SF-24-081 intercepted 1,339 grams per tonne silver over 9.5 meters , including 2,984 g/t Ag over 4.0m hole DZG-SF-24-089 intercepted 2,522 g/t Ag over 3.0m, including 7,052 g/t [...]
Aya Gold & Silver Inc. is pleased to announce interim financial and operational results for the second quarter ended June 30, 2024. All amounts are in US dollars, unless otherwise stated. Q2-2024 Highlights Solid operations in line with our plan: Silver production of 432,667 ounces . Ore processed increased to 80,562 tonnes , a 12% increase compared to Q2-2023. 114,025t of ore mined in the quarter for an average of 1,253 [...]
Aya Gold & Silver Inc. will release its Q2-2024 results on August 14, 2024 before market-open. Management will host a conference call on the same day, Wednesday, August 14, 2024, at 10 am EDT to discuss the Corporation's financial and operational results. Webcast link: https://edge.media-server.com/mmc/p/k6mm3jv7 Instructions for obtaining conference call dial-in numbers: All parties must register on the link below to [...]
Aya Gold & Silver Inc. is pleased to announce preliminary results from its recently completed regional geophysical survey of Boumadine in the Kingdom of Morocco. Today's results highlight multiple potential conductive anomalies with a similar or stronger response than the Boumadine anomaly. Key Highlights Completed an extensive 2024 regional airborne geophysical survey: The survey included high resolution magnetics and [...]
Aya Gold & Silver Inc. is pleased to announce that it has completed the inaugural silver pour at its expanded Zgounder Silver Mine in the Kingdom of Morocco. Highlights On July 2, the first silver pour was achieved: First silver bars were poured with silver cement from the existing cyanidation plant. First pour was an important step for the ongoing hot commissioning of the foundry and retort sub system. Commissioning [...]
Aya Gold & Silver Inc. is pleased to announce that it has completed commissioning of its electrical line and begun powering its Zgounder Silver Mine in the Kingdom of Morocco with renewable energy. Highlights On June 30, the 93km, 60kV power line was commissioned and powered: The departure and arrival substations have also been commissioned and energized. The line is connected to the Office National de L'Électricité et de [...]
Aya Gold & Silver Inc. is pleased to announce high-grade silver drill results from its at-depth drill exploration program at the Zgounder Silver Mine in the Kingdom of Morocco. Highlights In the Central Zone from the 1,950m level: hole DZG-SF-24-065 intercepted 2,870 grams per tonne silver over 6.5 meters , including 7,229 g/t Ag over 2.0m hole DZG-SF-24-057 intercepted 1,252 g/t Ag over 4.0m hole DZG-SF-24-070 [...]
Aya Gold & Silver Inc. is pleased to announce the beginning of commissioning activities at its new 2,000 tonnes per day mill at the Zgounder Silver Mine in the Kingdom of Morocco. Highlights Zgounder expansion over 95% complete. Pre-commissioning activities are ongoing in the main process plant areas, including the grinding circuit and the silver refinery as part of the commissioning process: Tests are being conducted on [...]
Aya Gold & Silver Inc is pleased to announce that it has completed its fourth and final drawdown under the previously announced US$100 million project financing facility for the expansion of the Zgounder Silver Mine in the Kingdom of Morocco. The Facility is jointly provided by the European Bank for Reconstruction and Development and by the Climate Investment Funds through its Clean Technology Fund . The fourth drawdown [...]
Aya Gold & Silver Inc. is pleased to announce that all nominees listed in the management proxy circular were elected as directors of Aya at its annual general meeting of shareholders held today. A total of 56,932,471 common shares or 48.92% of Aya's issued and outstanding common shares at the record date were represented in person or by proxy at the AGM. Detailed results are as below: Director Nominee Votes For % of Votes [...]